What problems is JUSTPRO MES solving and how is that benefiting you?
I was the project manager for this project, it was quite big project between Eaton and Glencore Xstrata, the project consists of 21 MCC control boards, each MCC is made of between 15 control cabinets to 20 control cabinets with sophisticated Allen Bradley PLC control, the project required quality and delivery on time, initially it was very difficult to keep track of purchasing, inspection, production and quality control, and without tracking it was difficult to deliver on time, then JUSTPRO was called in to implement JUSTPRO-MES system to interface with Oracle ERP, to manage the project from the design, construction, wiring, and factory acceptance test that achieved quality and allowed us to deliver on time, the project was successfully completed. Review collected by and hosted on G2.com.