Our standard net new deployment of our Universal Data Hub is 90 days. Deployment of AudienceStream alone may be shorter depending on steps already completed by the customer.  We follow a 5 step process that includes the following:

1 - Requirements gathering (tag specs, data requirements, use cases, segments)
2 - Data layer strategy (provide best practice recommendation to meet all requirements)
3 - Installation (customer implements Tealium Data Layer and universal tag on digital property, while Tealium begins initial configurations within the tool)
4 - Testing and Validation (Tealium to audit Data Layer, verify configurations meet specs)
5 - Go Live (release to production)


##### Comment Metadata
- Posted at: over 7 years ago
- Author title: Director of Product Marketing at Tealium




## Related Product
[Tealium Customer Data Hub](https://www.g2.com/products/tealium-customer-data-hub/reviews)

## Related Category
[Customer Data Platform (CDP)](https://www.g2.com/categories/customer-data-platform-cdp)

## Related discussions
- [How well does Trello scale into a larger team?](https://www.g2.com/discussions/1-how-well-does-trello-scale-into-a-larger-team)
  - Posted at: almost 13 years ago
  - Comments: 6
- [Can we please add a new section](https://www.g2.com/discussions/2-can-we-please-add-a-new-section)
  - Posted at: almost 13 years ago
  - Comments: 0
- [Quantifiable benefits from implementing your CRM](https://www.g2.com/discussions/quantifiable-benefits-from-implementing-your-crm)
  - Posted at: almost 13 years ago
  - Comments: 4