# After scheduling a baseline of any project in P6, we oftenly export cash flow. My question is, what date does P6 take as cutt off date for monthly cash flow for your project.

If time span of project is 12 months, P6 will give you a cumulative cash flow till 12th month. What date of the month does P6 take as a cutoff date when we draw S-Curve. Actually when I draw it manually in excel it gives different values and when I schedule P6 for my monthly reports it give different values.
Forexample: if you schedule P6 for 3rd month schedule % is 15.52% and when I check it from activity usage profile it is giving the value of 16.21%.

##### Post Metadata
- Posted at: over 5 years ago
- Author title: Project Planning Engineer at PRINCIPAL BUILDERS - Engineers &amp; Contractors
- Net upvotes: 1


## Comments
### Comment 1

Cut off date for monthly is up to the organization. Generally last friday or Thursday of the month is the cut off

##### Comment Metadata
- Posted at: over 5 years ago
- Author title: Planning Engineer at Subsea 7




## Related Product
[Oracle Primavera](https://www.g2.com/products/oracle-primavera/reviews)

## Related Category
[Capital Project Management](https://www.g2.com/categories/capital-project-management)

## Related discussions
- [How well does Trello scale into a larger team?](https://www.g2.com/discussions/1-how-well-does-trello-scale-into-a-larger-team)
  - Posted at: over 13 years ago
  - Comments: 6
- [Can we please add a new section](https://www.g2.com/discussions/2-can-we-please-add-a-new-section)
  - Posted at: over 13 years ago
  - Comments: 0
- [Quantifiable benefits from implementing your CRM](https://www.g2.com/discussions/quantifiable-benefits-from-implementing-your-crm)
  - Posted at: about 13 years ago
  - Comments: 4