# Why do the expected, required and promise dates differ between order, production and purchasing screens?

As a daily user I have found in the past that when reviewing the commitment schedule under the Item Master Inquiry, the dates between order and production screens were inconsistent. This caused an issue with having material ordered and delivered in time to build. Just because the screens may say expected date, required date, promise date, it seems like they are not consistent across all screens. I am unsure as to what date is pulled when viewing the commitment schedule and would like some concrete insight on that!

##### Post Metadata
- Posted at: about 6 years ago
- Author title: Customer Relations &amp; Engineering Project Scheduler | Wedding &amp; Event Planner
- Net upvotes: 1


## Comments
### Comment 1

Generally, these dates are driven by lead time information from the inventory supplier information. Often, the expected and required dates are the same. The promise date, however, is often blank, waiting for you to provide input from the supplier.

In my experience, unless you actively manage this information from the supplier, it&#39;s essentially useless.

##### Comment Metadata
- Posted at: about 6 years ago
- Author title: Managing Director at Insytes, LLC




## Related Product
[Epicor Prophet 21](https://www.g2.com/products/epicor-prophet-21/reviews)

## Related Category
[Distribution ERP](https://www.g2.com/categories/distribution-erp)

## Related discussions
- [How well does Trello scale into a larger team?](https://www.g2.com/discussions/1-how-well-does-trello-scale-into-a-larger-team)
  - Posted at: about 13 years ago
  - Comments: 6
- [Can we please add a new section](https://www.g2.com/discussions/2-can-we-please-add-a-new-section)
  - Posted at: about 13 years ago
  - Comments: 0
- [Quantifiable benefits from implementing your CRM](https://www.g2.com/discussions/quantifiable-benefits-from-implementing-your-crm)
  - Posted at: about 13 years ago
  - Comments: 4